Newport Harbor High School Aquatics Complex
February 2025

Construction Update

  • Concrete work at the bottom of the pool and the new interior building footing has been completed.
     
  • The pool walls, created by spraying concrete at high pressure, are completed.
     
  • Construction of the pool deck surge pit, which maintains a stable water level and prevents overflow around the pool deck, is in progress.
     
  • Installation of plumbing pipes in the existing building continues.
     
  • Ground-level concrete pour for the base of the aquatics buildings will begin soon.

Anticipated project completion: Fall 2025